Friday, August 12, 2016

Dry Docking

Documentation and Plans are required :

The Stability Information Plans and general particulars of the vessel.

The ‘General Arrangement Plan’.

The Dry Docking Plan.

A Tank Arrangement Plan.

The ‘Shell Expansion Plan’.

The ‘Plug Plan’ if not incorporated into the ‘Dry Dock Plan’.

The Rigging Plan.

The Ships Fire Fighting arrangement.

The Chief Officers ‘Repair List’.

Cargo plan (if appropriate).

Relevant certificates for respective survey work.



Preparation and precautions for entry :

All hatches and beams stowed (to give continuity of strength)

Derrick and cranes down & secured (to counteract roll)

Eliminate free surface

Adequate stability check (adequate GM to counteract the rise in ‘G’ due to ‘P’ force)

Consult dock authorities on draft and trim required.

Sound round all tanks and note all soundings in sounding book.

Security lock-up spaces

Lock-up toilets

Rig fenders.



When dry docking with cargo aboard :

Inform dock authorities where to position extra shores or blocks to take account of additional stresses caused by the weight of cargo aboard.

Give cargo areas a lock-up stow whenever possible.



When in dock :

Obtain telephone/electricity/water, pressure fire line, garbage and sanitation facilities as soon as possible.

Have documentation ready, inclusive of repair list, for dock personnel.

Should tank plugs need to be removed, sight their removal and retain the plugs for safe-keeping. Ensure that plugs are labelled after removal.



Checking after completion of docking :

Before flooding:

o Sound round all tanks. The soundings to be same as the initial soundings when the ship landed overall.

o Calculate the stability. The stability must match with the initial stability condition when the ship landed overall.

o All the plugs are in place and pressure tested.

o Grease removed from the transducer points.

o Anodes.

o Ship side markings

o Anchors heaved up.

o Paint dried up.

o Scaffoldings removed.

o Propeller and rudder are clear of any obstruction and cover.



While Re-floating :

o Inform E/R when flooding dock.

o Check for water tightness.

o Sound all tanks.

o Following times to be logged down:

Flooding commenced

Vessel floated

Dock gate opened

Vessel left dock.



After refloating :

o Check operation of all equipments.

o General cleaning and washing

o Normal sailing checklist.

o Check water tight integrity of the vessel.



Maintenance for Anchor in Dry Dock :

o Arrange in the dock.

o Water blasted.

o Check for thickness of the links (if 10% reduction from the original, then change the whole shackle).

o Cracks on the links (hammer tested).

o Correct marking.

o Overhauling of the bitter end.



Critical Instant :

o It is the instant just before the vessel takes blocks overall.

o The upthrust ‘P’ of bilge block acts on the stern frame.

o The upthrust ‘P’ will increase in direct proportion to loss of buoyancy as the water level falls.

o As the upthrust ‘P’ increases due to the falling water level, it has an increasing trimming effect on the vessel.

Trimming moment = P x LCF

Change of Trim (COT) = Trimming moment / MCTC

Therefore,

             P x LCF

COT = ------------------

             MCTC 
 

        COT x MCTC

P = -------------------

            LCF

o The upthrust ‘P’ is maximum at the critical instant.

o It is called critical instant because maximum loss of GM occurs at this instant.



If negative GM occurs in the Dry dock :

o The vessel will lose positive stability.

o She may capsize.

o She may slip off from the blocks.

0 comments:

Post a Comment